Four Burrows Wind Farm

Four Burrows Wind Farm, Cornwall

Four Burrows wind farm is situated near Truro, Cornwall.

Developed and constructed by New World Power in 1995, Four Burrows was purchased by Renewable Energy Systems Ltd in 1997.

The wind farm began generating power in March 1995 and was originally contracted under the 1994 Non Fossil Fuel Obligation (NFFO). Output is now contracted under the Renewables Obligation.


Information about the Project
line

Owner: RES-Gen Ltd
Developer & Construction Contractor: New World Power Ltd
Operation & Maintenance Contractor: RES-Gen Ltd
Installed Capacity: 4.5 MW
Number of Turbines: 15
Turbine Rating: 300 kW
Turbine Type: Siemens Combi MKII (Stall-regulated)

 

 


Home | RES Group | Wind Farms | Wind Power | Heat and Power | Beaufort Court | News | Contact Us